The working group for signage and lining will develop a signage programme for North Clare. The group will also focus on identifying signs and markings that require renewal. Drive on left signs and markings will be installed at tourist locations. Suitable locations for walkers on roads signs will also be identified and a communications programme with local businesses will be rolled out to encourage guests to drive on regional and national roads where possible.
Actions | KPI | Target Date |
---|---|---|
MD should document work done to date eg road north of Kilfenora |
Register of works/interventions made produced | Q2 2024 |
Develop signage programme for the North Clare Area – medium term |
Signage plan for North Clare Area agreed | Q2 2025 |
Support & Implement ‘Drive on Left ‘ signage/lining at exits of tourist locations and carparks – summer 2024 |
Record locations where signage lining is installed | Q2 2024 |
Identify locations that require renewal & maintenance to signs and lines |
Programme for renewal & maintenance developed | Q2 2024 |
Support and Implement locations suitable for ‘walkers on the road’ signage | Map locations | Q2 2024 |
Identify locations where space in verge can be provided as pedestrian refuge |
Map locations | Q2 2024 |
Updates
There are no updates currently in this section of the website.
Content managed by: Roads, Environment and Water Services Department
Back to topThis is just for feedback on our web site, not comments or questions about our services.
To tell us about anything else, go to our contact us pages.