The working group for traffic management and pedestrian facilities will consider issues in relation to traffic and safety measures for pedestrians and cyclists. Included in the measures to be considered are traffic surveys to be completed during 2024, periodic speed limits at some schools, the identification of locations for gateway or traffic calming measures, the assessment of cycling routes as well as progressing active travel pedestrian and cycling measures.

Actions, KPIs and target dates

 
Actions KPI Target Date

Manage the collection of traffic data in North Clare in June & August 2024 - Kilfenora, Corofin, Ballyvaughan, Corkscrew, Lemanagh, Doolin, Ballinalaken Junction, Lisdoonvarna, Kilnaboy.

Traffic Survey completed

Q2/Q3 2024

Periodic Speed Limits at Schools - identify candidate locations in North Clare advance of new speed limit guidance

Prepare list of schools suitable for periodic speed limit

Q2 2024

  • Progress Byelaws for Periodic Speed Limits at N67 Rinneen and N67 New Quay.
  • Implement Proposed National speed limit review

Byelaws adopted

National Guidance

Q3 2024

Q3/Q4 2024

Identify & prioritise locations for gateway treatment/traffic calming - e.g. Fanore, Kilfenora, Kilnaboy.  Identify suitable funding streams - Towns & Village Renewal, Low Cost Safety, Specific Improvement Schemes, Development Fund etc.

Submit funding applications to DDTAS or Towns & Villages Renewal

DDTAS - Q3 2024

Cycling Routes

  • Doolin Cycle Hub Loop 1
  • Doolin Cycle Hub Loop 2
  • Doolin Cycle Hub Loop 3
  • Doolin Cycle Hub Loop 4

assessed to verify their condition and complince with the current Recreational Cycling Trails Criteria for Ireland

Complete assessment

Q2 2024

RDO Progressing pedestrian crossing design Lahinch& Inagh.

Approval granted from TII to proceed to construction

Q2 2024

Active Travel Pedestrian and Cycling Connectivity Bridge Assessment carried out - O'Briens Bridge Liscannor - consider implementation.

Conclude Bridge assessment report

Q2 2024

Identify funding stream for pedestrian facilities Doolin

Q2 2024

Review 2007 Coast Road Strategy Report

Potentially engage with consultants to update report

Q2 2024




 